Difference between revisions of "Case Study Committee Workplan"

From COST Action FP0804: FORSYS
Jump to: navigation, search

Warning: require(): Unable to allocate memory for pool. in /data/home/fp0804/www/wiki/includes/AutoLoader.php on line 1191
m
Line 3: Line 3:
 
<div style="float:right;">__TOC__</div>
 
<div style="float:right;">__TOC__</div>
  
===Timeline===
+
==Timeline==
 
* 18th November 2011 – FORSYS participants submit STSM opportunities to wiki
 
* 18th November 2011 – FORSYS participants submit STSM opportunities to wiki
 
* 1st  February 2012 – FORSYS participants submit case study (CS) abstracts to CS technical committee (CSTC)
 
* 1st  February 2012 – FORSYS participants submit case study (CS) abstracts to CS technical committee (CSTC)
Line 37: Line 37:
 
===After the Leuven 2011 meeting===
 
===After the Leuven 2011 meeting===
 
* Synthesize Leuven discussion and update [[Case Study Guidelines]] on the wiki
 
* Synthesize Leuven discussion and update [[Case Study Guidelines]] on the wiki
* Developed semantic wiki form for STSMs
+
* Developed semantic wiki form for [[STSM Opportunities]]
  
 
===Before the Leuven 2011 meeting===
 
===Before the Leuven 2011 meeting===

Revision as of 04:13, 11 January 2012

Timeline

  • 18th November 2011 – FORSYS participants submit STSM opportunities to wiki
  • 1st February 2012 – FORSYS participants submit case study (CS) abstracts to CS technical committee (CSTC)
  • 1st March – CSTC provides reporting format for CS
  • 1st March - CSTC responds to abstracts
  • 1st June - CSTC follow up on cases
  • 1st September – FORSYS participants submit first draft of CS to CSTC
  • 1st October – CSTC responds to drafts
  • 1st November – FORSYS participants submit final CS
  • 20th December 2012 – CSTC synthesis
  • 2013 CS synthesis informs development of FORSYS guidelines
  • technically have until 3 months after end of project (4/2013) to complete all project work

Develop case study guidelines

  • Figure out how cases will contribute to final Forsys guidelines
  • E-mail Forsys participants about important guidelines updates

Manage case study contributions

  • Develop semantic form for entering case studies into the wiki
  • Solicit case studies from the Forsys network
  • Review and comment on case studies submitted
  • Answer questions, resolve issues

Case study literature database

  • Investigate possible technologies for managing/sharing case study literature

Publications

  • Think of publication possibilities for case study work


DONE

After the Leuven 2011 meeting

Before the Leuven 2011 meeting

  • Develop two (or more) documents:
  • Gather further information on case studies (STC sends request to country representatives)
    • Existing forest DSS case studies
    • Potential forest DSS case studies
    • Other relevant literature (methods, theories, etc)

At Leuven 2011 meeting

  • Give case study introductory presentation
  • Each STC member leads a subgroup on assigned task
  • Develop & present a time line for the work on the case studies
    • incl. meeting of the STC
    • incl. clear division of responsibilities