Difference between revisions of "Participatory planning case template"
From COST Action FP0804: FORSYS
(→Brief overview) |
(→Organization) |
||
Line 19: | Line 19: | ||
== Organization == | == Organization == | ||
− | * Who | + | * Who started the process? |
− | * What | + | * What influence did the participation have in the decision process? (for instance compared to Arnstein levels of participation) |
− | * How is the participation process organized? | + | * How is the participation process organized? |
+ | * What was the time frame for participation? | ||
+ | * What was the time frame related to the project time frame? | ||
+ | * What was the budget of project/participation (for example in money, workdays etc.)? | ||
+ | |||
+ | ===Problem structuring === | ||
+ | * How was the problem defined? | ||
+ | * Who defined the problem? Was participation used in problem definition phase? | ||
+ | * What tools or methods were used in problem structuring, if any? | ||
== Intelligence == | == Intelligence == |
Revision as of 16:02, 26 November 2009
General case description
Brief overview
Briefly define purpose & objectives of the case introduced
- what was the problem
- what was the end product
- what was the planning area
- what was the planning organization
- who was the decision maker
- what were the aims of the project
- what were the aims of the participation process in the project (for example, conflict resolution, increasing acceptance of decisions)
Contents
Organization
- Who started the process?
- What influence did the participation have in the decision process? (for instance compared to Arnstein levels of participation)
- How is the participation process organized?
- What was the time frame for participation?
- What was the time frame related to the project time frame?
- What was the budget of project/participation (for example in money, workdays etc.)?
Problem structuring
- How was the problem defined?
- Who defined the problem? Was participation used in problem definition phase?
- What tools or methods were used in problem structuring, if any?
Intelligence
Stakeholders
- who were the stakeholders?
- how were they selected?
Objectives
- what were the criteria?
- how were they selected?
Preferences
- how were the preferences of the decision makers and stakeholders elicited?
Information
- what information was collected?
- what tools were used for data collection?
Design
Alternatives
- What kind of alternatives were considered?
- How were they defined?
- Who defined them?
Choice
Usage of DSS
- What kind of DSS was used (if any)?
- How was the DSS used in the process?
Usage of models, methods and tools
- What kind of decision support tools (models, methods) were used, if any?
Monitoring
- Was the implementation of the plan monitored?
- Was the success of the process monitored?
- How was the success of the process monitored?
References
Cited references